Pioneer Trail II Underground District

Project Summary

The Pioneer Trail Phase II Underground District Project is a project to replace approximately 1.2 miles of existing overhead utility lines along Pioneer Trail between Golden Bear Trail and Black Bart Avenue. The new electric, cable, and telephone lines will be located in underground conduit and vaults along Pioneer Trail. The project is made possible through the Rule 20.A utility program.


​Documents

​Relevant Project Links

​Project Schedule

 Location and Activity  Estimated Start Date / Duration
 Pioneer Trail and all side streets - install erosion control devices 5-23-2016 / 5 days
 Pioneer Trail - trenching, conduit, and box installation 6-14-2016 / 4 months
 Black Bart Court - trenching, conduit, and box installation  5-31-2016 / 11 days
 High Meadow Trail - trenching, conduit, and box installation  6-27-2016 / 7 days
 Fair Meadow Trail - trenching, conduit, and box installation  7-18-2016 / 5 days
 Marshall Trail - trenching, conduit, and box installation  8-8-2016 / 7 days
 Kokanee Trail - trenching, conduit, and box installation  8-29-2016 / 7 days
 Golden Bear Trail - trenching, conduit, and box installation  9-20-2016 / 9 days