Project Name
|
Project Descriptions
|
Fiscal Year To Construction
|
Total Project Budget
|
Highway 50 Interchanges
|
Save
|
HOV lane extension
|
Extend HOV lanes to base of Bass Lake Hill Grade. Project will include replacement of the El Dorado Hills Blvd and Silva Valley Parkway bridges.
|
07/08
|
$19,575,000
|
El Dorado Hills Blvd Interchange Pedestrian Over crossing
|
El Dorado Hills Blvd interchange Pedestrian Over Crossing.
|
09/10
|
$3,187,000
|
El Dorado Hills Blvd Interchange Phase 1.2A Saratoga Realignment
|
Improvements consist of the realignment of the west leg of Saratoga Way to Park Dr the and widening of southbound El Dorado Hills Blvd. Construction to be completed in fall 2005.
|
04/05
|
$6,965,495
|
El Dorado Hills Blvd Interchange Phase 1.2B Ramp Enhacements
|
Interim improvements to the westbound on and of ramps and improvements to Northbound El Dorado Hills Blvd underneath Highway 50. Construction to be completed in fall 2005.
|
05/06
|
$2,821,212
|
Missouri Flat Interchange Phase 1A
|
Reconstruction of the existing interchange into a tight diamond configuration with four thru-lanes on Missouri Flat Road from Prospector Plaza to Mother Lode Dr; including auxiliary turn lanes, transition lanes and signals/intersection improvements at the intersections of Mother lode Dr, the eastbound/westbound ramps and Prospector Plaza Dr.
|
06/07
|
$32,159,397
|
Missouri Flat Interchange Phase 1B
|
Improvements include: an eastbound auxiliary lane on US 50 from Missouri Flat Rd to Forni Rd; reconstruction and/or widening of all existing ramps and a free right turn lane from Northbound Missouri Flat Rd to Eastbound US 50 with a realigned Perks Court also included.
|
07/08
|
$24,840,603
|
Silva Valley Rd Interchange
|
Phased improvements to provide a new interchange on Highway 50 at Silva Valley Parkway/White Rock Road.
|
08/09
|
$46,250,000
|
Bass Lake Rd Interchange
|
Preliminary engineering and enviromental review for improvements at the Highway 50 at Bass Lake Road interchange.
|
12/13
|
$31,200,000
|
Cambridge Rd Interchange
|
Phased improvements include: Signalize intersection of Merrychase and Cambridge and construct related improvements.
|
05/06
|
$1,088,342
|
Cambridge Rd Interchange
|
Preliminary engineering and enviromental review for phased improvements at the Highway 50 at Cambridge Road interchange.
|
12/13
|
$35,510,000
|
Cameron Park Dr Interchange
|
Phased improvements at: 1)Cameron Park Dr@Palmer Dr (72364)2)Cameron Park Dr@Country Club Dr (72363) 3) Cameron Park Dr@Coach Lane (66112).
|
05/06
|
$4,650,000
|
Cameron Park Dr Interchange
|
Phased improvements at the Highway 50 at Cameron Park Dr interchange.
|
09/10
|
$31,918,481
|
North Shingle Rd/Ponderosa Rd I/C
|
Phased improvements at the Highway 50 at North Shingle Rd/ Ponderosa Rd interchange.
|
09/10
|
$43,460,000
|
El Dorado Rd I/C
|
Preliminary engineering and enviromental review for improvements at the Highway 50 at El Dorado Road interchange.
|
08/09
|
$6,880,000
|
Missouri Flat Area
|
Pleasant Valley Rd/Missouri Flat Connector
|
Design, enviromental review and Right of Way acquisitions for two lane connector between Missouri Flat Rd and Highway 49.
|
07/08
|
$12,210,000
|
|
Cameron Park Dr and Meder Rd intersection improvements
|
Improvements consist of installation of traffic signals along with pavement widening to accommodate auxiliary right turn lanes and expansion of existing two way left-turn lanes. Construction complete, final expenditures in 05/06.
|
04/05
|
$1,242,862
|
Cameron Park Dr and Mira Loma Dr intersection improvements
|
Improvements consist of left turn Lanes both northbound and southbound. Construction complete, final expenditures in 05/06.
|
04/05
|
$1,186,445
|
Cameron Park Dr- Improvements Palmer Dr to Green Valley Rd
|
Improvements at Oxford Rd (72365) & La Canada Dr (72366) intersections to include installation of traffic signals along with widening to accommodate auxiliary right turn lanes and expansion of existing two-way left turn lanes at both intersections.
|
06/07
|
$3,518,376
|
|
Green Valley Rd / Silva Valley Parkway intersection improvements
|
Improvements include: signalization of the intersection, construction of left turn lanes and addition of crosswalks.
|
05/06
|
$2,244,657
|
Green Valley Rd County line to Francisco Dr
|
This is the final phase of improvement to this section of Green Valley Rd. This final phase adds a 3rd & 4th lanes as well as a signal at Browns Ravine. Plus the conversion of the overhead utilities lines to underground.
|
05/06
|
$8,307,446
|
El Dorado Hills Blvd Intersection realignment and signalization with Francisco Dr
|
Improvements to include the realignment of El Dorado Hills Blvd and Francisco Dr and Brittany Way and approach roadways resulting in a new 4-way intersection with extension and signal installations.
|
07/08
|
$5,033,559
|
Saratoga Extension
|
Design, enviromental review and construction of new two lane road.
|
06/07
|
$10,000,000
|
Latrobe Rd widening White Rock Rd to Suncast Lane
|
Improvements to consist of widening Latrobe Road from two to four lanes between White Rock road and Suncast Lane including improvements to impacted intersections and signals. Construction complete, final expenditures in 05/06.
|
04/05
|
$6,933,113
|
White Rock Rd extension Latrobe Rd to 5th Ave
|
Improvements to include: upgrading White Rock Rd to one full lane in each direction with shoulders. Improvements also include providing turn lanes at intersections and major driveways. Construction complete, final expenditures in 05/06.
|
04/05
|
$2,164,521
|
Intersections & Turn Pockets
|
Intersection Improvements- Pleasant Valley Rd and Patterson Dr
|
Improvements to include signalization of the intersection along with various improvements.
|
06/07
|
$1,000,000
|
Intersection Improvements- Durock Rd and Business Center Dr
|
Improvements to include signalization of the intersection along with various improvements.
|
06/07
|
$1,400,000
|
Intersection Improvements- El Dorado Rd and Motherlode Dr
|
Improvements to include signalization of the intersection along with various improvements.
|
05/06
|
$1,000,000
|
Intersection Improvements- Missouri Flat Rd and El Dorado Rd
|
Improvements to include signalization of the intersection along with various improvements.
|
05/06
|
$1,242,377
|
Intersection Improvements- Mother Lode Dr and Pleasant Valley Rd
|
Improvements to include signalization of the intersection along with various improvements.
|
08/09
|
$2,000,000
|
Intersection Improvements- Missouri Flat Rd and Golden Center Dr
|
Improvements to include signalization of the intersection along with various improvements.
|
05/06
|
$1,400,000
|
Pleasant Valley Rd Left Turn Lanes-Toyan Dr to Pearl Place
|
Improvements to include: construction of two way left turn lane on Pleasant Valley Rd from Toyan Dr to Pearl Place.
|
05/06
|
$2,623,323
|
Mother Lode Dr (So Shingle Rd to No Star Dr) (Add L-Turn pockets/2-wy turn-lanes)
|
Improvements to include: construction of two-way left turn lanes on Motherlode Dr from South Shingle to French Creek.
|
06/07
|
$1,177,562
|
Bridges & Studies
|
Green Valley @ Dry Creek Bridge
|
Replace existing bridge over Dry Creek and realign roadway to create a T intersection at Lotus Road. Project is complete.
|
04/05
|
$3,588,927
|
Green Valley @ Tenn Creek Bridge
|
Proposed bridge replacement over Tennessee Creek as well as improvements and realignments at Green Valley Road.
|
07/08
|
$3,206,589
|
Green Valley @ Weber Creek Bridge
|
Proposed bridge replacement over Weber Creek as well as improvements and realignments at Green Valley Road.
|
09/10
|
$7,795,000
|
Mt Murphy Bridge "Study" |
Approved study to analyzse alternative to mitigate exisiting deficiencies to the bridge. The study will examinethe potential improvements and recommend a preferred alternative. |
05/06
|
$286,491
|
US Highway 50 thru Camino "Study" |
Conversion of the expressway to a freeway and construction of anew interchange. El Dorado County is pursuing an alternative project that could relive some of the existing access issues. Current contributions are for this alternative study. |
07/08
|
$2,000,000
|
|
|
Plus: RIF Reimbursement agreements
|
|
$35,843,117
|
|
Plus: TIM Reimbursement agreements |
|
$372,066,778 $1,661,300
|
Commuter Buses
|
This item is for the purchase of fleet expansion buses for Highway 50 commute services. Five buses will be purchased in fiscal year 05/06.
|
Every 3rd yr
|
$5,000,000
|
|
Total |
|
$414,571,195
|