Master Plan Program
A master plan is essentially a "cookie cutter" plan that will be built repetitively. The Master Plan Program establishes a site specific building design approval protocol that is predictable and dependable for an unlimited number of building permits in the current
3-year code cycle. You can achieve standardization and consistency in the construction process and the time spent during the site specific application is reduced drastically with consistent submittals. The program is limited to licensed contractors with a current
California State Contractors license and a current
El Dorado County business license.
Master plans cannot be bought, traded, or transferred from one contractor/developer or jurisdiction to another.
The Master Plan Program consists of two parts; the master plan and the site specific application. A construction plan is submitted and reviewed for code requirements and once approved, assigned a specific master plan number for future reference. The site specific application is the submittal of a particular master plan on an individual parcel.
The Master Plan Program is not limited to large subdivisions. If you plan to use the same building design on different parcels throughout the county the program will work for you.
Guidelines
MASTER PLAN PROGRAM
- All plans must be submitted with left and right-hand orientation.
- Site plans for subdivision lots are required to be in an 8-1/2" x 14" format.
- Elevations are limited to a total of four.
- The plan is limited to three different garage footprints (typically 3-car, 4-car, and side-load garage options). The living space footprint cannot be altered.
- A single foundation plan is required to accommodate any approved elevation or approved option within that particular plan. The foundation must be built to this worst-case specification.
- Structural revisions to the plan are not permitted (i.e.: footings, bearing walls, shear walls, window locations, or roof layout). Such a plan would require submittal as a separate master plan, or could be submitted as a custom home (still handled by our master plan staff for continuity).
- Non-structural revisions are permitted. Generally, only a revised floor plan would need to be submitted (no options shown). However, if a gas appliance was added or re-located, a revised gas-piping plan would also be required.
- Field revisions are discouraged, but if the scope is limited, they may be accepted due to the nature of the industry. However, continued and/or excessive revisions to master plans will cause our department to evaluate the builder's status within the program, and whether both parties would be better served by the builder using the mainline permit system for future submissions.
Submission
MASTER PLAN SUBMITTAL
MASTER PLAN SUMMARY
In order for the plan review process to begin the following items must be submitted:
- Complete a
"Master Plan Submittal" form
- Submit a square-footage summary of the plan variations using the
“Master Plan Summary"
- One complete set of construction plans.
- Structural calculations and applicable plan pages must be wet-stamped and signed by the Engineer or Architect of Record. Note that construction drawings and related submittals by design professionals must acknowledge the repeated use of their work.
- Truss specifications must be wet-stamped by the truss engineer. The project engineer (Engineer of Record) must also review, stamp and sign the truss layout sheet for compatibility with the building design.
- A truss layout sheet per elevation (compatible with the roof plan).
- Energy calculations for all orientations. Design must meet worst-case scenario.
- Left and right-hand plans (so the building can be reversed). Applies to all structural pages (i.e: foundation, floor framing, shear walls, roof-framing). Also provide a reversed floor plan.
- Shear wall schedule on same sheet(s) as shear layout where practicable.
- Gas piping plan showing pipe length, size and input BTU demand of each appliance. Specify type of fuel.
- Electrical/mechanical plan.
Application
SITE SPECIFIC APPLICATION CHECKLIST
Submitting a site-specific application to obtain a permit:
- Submit 2 copies of an 8-1/2” x 14” site plan drawn to a 1:20 scale (1:30 may be used for lots too big to fit the page drawn at 1:20).
- Submit a completed permit application with master plan number written in description of work. Include bedroom count on application.
- Submit 3 copies of the site-specific floor plan (verify left or right hand, and only show options that apply).
- Submit 2 copies of the exterior elevation drawings. Orientation is not required.
- Provide a map page locating the site, if necessary.
- Submit a check for the application fee, with a list of the lot numbers you are applying for and fee amount per lot (see attached fee schedule).
Submitting a revision to a site application (changing from one MP # to another):
- Submit a signed letter requesting that the change be made. Specify the MP # and lot involved, refer to the permit number if this is an issued permit.
- Submit 2 revised site plans, if applicable, with the new master plan number written on each page.
- Submit 3 revised floor plans with the new master plan number written on each page.
Fees
The minimum flat rate is $600 for dwellings under 1000 sq. ft. Garage, deck, storage, and other miscellaneous areas are not included in the calculations. The rate increases in 00 increments for each additional 500 sq. ft. of dwelling area.
Master Plan Fees
DWELLING AREA sq. ft. |
FLAT RATE Dollars |
Under 1000 | $600 |
1000 to 1499 | $800 |
1500 to 1999 | $1,000 |
2000 to 2499 | $1,200 |
2500 to 2999 | $1,400 |
3000 to 3499 | $1,600 |
3500 to 3999 | $1,800 |
4000 to 4499 | $2,000 |
4500 to 4999 | $2,200 |
Additional 500 sq. ft. increments | $200 per increment |